IESO recommends Hydro One move forward with 2nd phase of Waasigan line
Ontario’s Independent Electricity System Operator (IESO) is recommending that Hydro One move forward with the second phase of its Waasigan Transmission Line.
The second portion of the project would see construction of a transmission line between Atikokan and Dryden, following completion of the first stage between the Mackenzie transformer station east of Thunder Bay to Atikokan..
Stating that the additional 230-kilovolt transmission line is needed to meet the future electricity needs in northwestern Ontario’s mining sector, IESO transmission planning director Ahmed Maria recommended that phase two should be in-service as close to the end of 2025 as possible.
“We spoke with businesses in the area, with communities, with First Nation communities as well, to understand how demand for electricity in that region is growing, and what we are forecasting is demand for electricity in the west of Thunder Bay will be increasing due to development of new mines, expansion of existing mines, and the electrification of mining activity,” Maria said.
Maria acknowledged that 2025 is a conservative timeline for the Waasigan transmission line to be completed in full, but he said that over the next decade Northwestern Ontario will see a significant mining boom and the industry’s need for electricity will double.
Hydro One is currently reviewing the final route for the transmission line, with the first phase having been met with contention by Kaministiquia area residents. The route, which parallels an existing transmission line, has numerous property owners stating that the lines will cross onto their land and, in some cases, pass right over their houses.
When asked if concerns from a community group affected the recommendation, Maria said the role of the IESO is to supply companies like Hydro One with data on the demand for electricity across the province. Hydro One uses the data to provide to working with affected communities on the routing of the line.
“It’s entirely within Hydro One’s responsibility to figure out the appropriate routing for the line,” said Maria.
Hydro One project delivery director Sonny Karunakaran said the ISEO announcement is “fantastic news.”
“It gives us the green light and clarity on the expectations of when phase two is to be put into service,” said Karunakaran.
Karunakaran acknowledges that they still have some construction planned to do for phase two, but he is optimistic that Hydro One will be ready to start phase two as soon as phase one is energized.
The first phase of the Waasigan Transmission Line is currently on track to be completed closer to 2025, according to Karunakaran. Although he admits that there are certain “things on the project that we’ll continually monitor and update on forecasted plans.”
The first phase still needs to go through an environmental assessment and comment period. Karunakaran said that a draft will be released in the coming weeks.
Afterwards, Hydro One will need to file for a leave to construct application with the Ontario Energy Board for both phases of the project.
“All pointing toward activities with construction in 2024,” said Karunakaran.
The Waasigan Transmission Line is a 50/50 equity partnership with nine First Nations, including Fort William First Nation. – tbnewswatch.com
article website here
Why is nobody wondering why we are spending billions to build infrastructure that can be wiped out at any time by a single solar CME? Would it not be better to build additional generation sources closer to the place where the electricity is needed instead of stringing hundreds and hundreds of kilometers of cable across the region?
What is the back-up plan when, not if, our electricity grid goes down? Nobody is talking about that. We are become more and more dependent on electricity.
Think about it. There is no Plan B. We need a Plan B.